Back to Top
welcome banner

Home

  
  
  
Rollup Image
Page Content
  
17/07/2018Rue du Crocquet and Mont de la Rocque closures

We have been advised by the JEC that the electricity supply in the High Street is proving to be inadequate for current and expected demand.

Recent experiences in Market Hill show that the connections need to be upgraded as soon as possible, this means an 8 week closure of the High Street and approx. 1 week on Mont de la Rocque.

We understand that this application is highly inconvenient and therefore the work will not commence until the end of September 2018 at the earliest, although trial pits will be carried out in the near future these will only involve a few days closure.

The JEC will letter drop all affected residents shortly, providing a plan of the affected areas.

If you have any questions regarding the above please do not hesitate to contact the JEC Customer Care Team on 505460.

  
18/05/2018Final Resurfacing

The Department for Infrastructure is due to commence the final part of highway maintenance work in St Peter’s Valley in late May / early June 2018.

The maintenance work will involve the provision of a new surface called Microasphalt (MA) which will be laid directly on top of the existing road surface. This resurfacing treatment has been completed successfully on a number of projects throughout Jersey. A selection of some of these projects are listed below:

 Green Road – St Clement

 A section of La Route D'Ebenezer - Trinity

 Mont Cochon – St Helier

The contractor undertaking the work will be Eurovia Ltd who have over 30 years’ experience working in the highway industry.

The key advantages in adopting this form of resurfacing treatment are listed below:

 Speed of construction is significantly quicker when compared to alternative forms of resurfacing;

 Highly cost effective solution when compared to other forms of surface treatment; this has enabled St Peter’s Valley and St Aubin’s Road to be resurfaced from Rue de Galet to the Elms.

The attached map indicates the full extent of the areas where this maintenance work will be undertaken and also indicates the traffic management and working hours for each phase. Please note the anticipated start date for the work is end of May 2018 with a completion date of mid-June 2018. We will contact you shortly with anticipated start / finish dates for each phase.

To enable the work to be undertaken in a safe and efficient manner, we have to undertake the majority of the work under full road closures. For each phase of the work, a detailed diversion route will be provided, which will be issued at a later date. Access to premises will be maintained at all times other than those days when surfacing work is being undertaken.

The Department for Infrastructure apologises in advance for any disruption caused by these works. Should you wish to discuss any item mentioned above or require further information please do not hesitate to contact Barry Nolan at barry.nolan@gov.je or on Tel 07829 782925.

StPeterValley.png

  
16/05/2018Useful information for the Elections on 16 May

​Closing date to register is 12 noon on Monday 9 April.

If you have never been on the Electoral Regsiter before you have until 12 noon on Wednesday 9 May.

If you are registered by the 9 April and are busy on Election Day you can do a pre-poll vote from 30 April at St Pauls Centre or 5 May at Trinity Youth Centre, or 12 May at Communicare, St Brelade.

If you will be away for the Elections and are unable to make it to the pre-poll stations you can apply for a Postal Vote, details can be obtained by visiting www.vote.je .

If you are suddenly ill on the day of the Elections or are hospitalised, then you should phone the Parish Hall to arrange for a "sick on the day" vote to be collected from you.

Don't forget that in order to vote you will need to bring with you photographic ID such as a driving licence or passport.

For further information please visit www.vote.je

1 - 3Next
  
  
Rollup Image
  
  
There are no items to show in this view of the "Events" list.
  
  
  
Rollup Image
Page Content
  
17/07/2018Rue du Crocquet and Mont de la Rocque closures

We have been advised by the JEC that the electricity supply in the High Street is proving to be inadequate for current and expected demand.

Recent experiences in Market Hill show that the connections need to be upgraded as soon as possible, this means an 8 week closure of the High Street and approx. 1 week on Mont de la Rocque.

We understand that this application is highly inconvenient and therefore the work will not commence until the end of September 2018 at the earliest, although trial pits will be carried out in the near future these will only involve a few days closure.

The JEC will letter drop all affected residents shortly, providing a plan of the affected areas.

If you have any questions regarding the above please do not hesitate to contact the JEC Customer Care Team on 505460.

  
18/05/2018Final Resurfacing

The Department for Infrastructure is due to commence the final part of highway maintenance work in St Peter’s Valley in late May / early June 2018.

The maintenance work will involve the provision of a new surface called Microasphalt (MA) which will be laid directly on top of the existing road surface. This resurfacing treatment has been completed successfully on a number of projects throughout Jersey. A selection of some of these projects are listed below:

 Green Road – St Clement

 A section of La Route D'Ebenezer - Trinity

 Mont Cochon – St Helier

The contractor undertaking the work will be Eurovia Ltd who have over 30 years’ experience working in the highway industry.

The key advantages in adopting this form of resurfacing treatment are listed below:

 Speed of construction is significantly quicker when compared to alternative forms of resurfacing;

 Highly cost effective solution when compared to other forms of surface treatment; this has enabled St Peter’s Valley and St Aubin’s Road to be resurfaced from Rue de Galet to the Elms.

The attached map indicates the full extent of the areas where this maintenance work will be undertaken and also indicates the traffic management and working hours for each phase. Please note the anticipated start date for the work is end of May 2018 with a completion date of mid-June 2018. We will contact you shortly with anticipated start / finish dates for each phase.

To enable the work to be undertaken in a safe and efficient manner, we have to undertake the majority of the work under full road closures. For each phase of the work, a detailed diversion route will be provided, which will be issued at a later date. Access to premises will be maintained at all times other than those days when surfacing work is being undertaken.

The Department for Infrastructure apologises in advance for any disruption caused by these works. Should you wish to discuss any item mentioned above or require further information please do not hesitate to contact Barry Nolan at barry.nolan@gov.je or on Tel 07829 782925.

StPeterValley.png

  
16/05/2018Useful information for the Elections on 16 May

​Closing date to register is 12 noon on Monday 9 April.

If you have never been on the Electoral Regsiter before you have until 12 noon on Wednesday 9 May.

If you are registered by the 9 April and are busy on Election Day you can do a pre-poll vote from 30 April at St Pauls Centre or 5 May at Trinity Youth Centre, or 12 May at Communicare, St Brelade.

If you will be away for the Elections and are unable to make it to the pre-poll stations you can apply for a Postal Vote, details can be obtained by visiting www.vote.je .

If you are suddenly ill on the day of the Elections or are hospitalised, then you should phone the Parish Hall to arrange for a "sick on the day" vote to be collected from you.

Don't forget that in order to vote you will need to bring with you photographic ID such as a driving licence or passport.

For further information please visit www.vote.je

1 - 3Next
  
  
Rollup Image
  
  
There are no items to show in this view of the "Events" list.